After the Fall of Pier Head Formwork on the Construction of BORR Toll Road Section III A, Material Handling and Cleaning Around the Site Has Been Done
Jakarta - On Tuesday, July 10, 2019 at 05:15 a.m. morning there had been an incident of the formwork falling during the casting of Pier Head work on the construction of the Bogor Ring Road Toll Road (BORR) III A section of Yasmin-Simpang Semplak section A on the Simpang Yasmin section. point P109. Based on the results of information provided from the team in the field at the time of the incident, there were no fatalities in this incident.
At present, PT. Marga Sarana Jabar (MSJ) has instructed the team in the field to check on the scene. Then after checking, it will be carried out cleaning the material that falls down blocking the road body as a first step of handling until the handling time at 13.00 WIB and then the vehicle can pass back normally.
At present, closure is being carried out on the Soleh Iskandar road in both directions, and anticipating the density of traffic movements for the time being the vehicle is diverted through the Atang Sanjaya road. PT. Marga Sarana Jabar as a Toll Road Business Entity (BUJT) apologizes for the inconvenience that has plagued road users, and it is hoped that road users will continue to be careful in driving so that they reach their destination.
It will also stop the temporary work and thoroughly evaluate the Contractor PT. PP (Persero) Tbk and executive consultant of PT. Indec KSO regarding the improvement of work implementation in order to avoid incidents occurring in the future to be more careful in accordance with Occupational Health and Safety Procedures (K3).
The Ministry of PUPR has asked BUJT and the implementing contractor to immediately prepare control measures and continue to work in improving the supervision of the implementation of existing work methods and OHS procedures. So that the Team of Bridge and Road Tunnel Security Commission (KKJTJ) will be deployed to directly observe the location of the Section 3A Bogor Ring Road Toll Road (Simpang Yasmin-Simpang Semplak).
BPJT instructs all Toll Road Business Entities (BUJT) and implementing contractors to implement Occupational Health and Safety Management System (SMK3) which has been regulated in the Minister of Public Works Regulation Number 5 / PRT / M / 2014 concerning Guidelines for Occupational Health and Safety Management Systems (SMK3) ) Construction of the Public Works Field. The BPJT will further activate the PMI consultant (Independent Quality Controller) to ensure compliance of business entities in carrying out construction work. Internal supervision from BUJT on implementing contractors must also continue to be more stringent in the implementation of toll road construction activities in order to avoid recurrence of similar events.