Minister Basuki Asked Cisumdawu Toll Land Handling to Be Accelerated

Minister Basuki Asked Cisumdawu Toll Land Handling to Be Accelerated

Sumedang - Taking advantage of the National Holiday of the Death of Isa Al Masih, Friday (2/4), Minister Basuki reviewed the construction of the Cileunyi - Sumedang - Dawuan (Cisumdawu) Toll Road, West Java.

Minister Basuki asked all parties to continue to coordinate and work hard to accelerate land acquisition, so that the completion of the Cisumdawu Toll Road is in line with the final 2021 target.

This 60.10 km toll road will be connected to the Kertajati Airport Access Toll Road and is expected to improve connectivity to the Kertajati West Java International Airport (BIJB) which has started operating.

The Cisumdawu toll road consists of 6 sections with the following construction progress:

Section 1 Cileunyi-Rancakalong (11.45 km) 71.59%

Section 2 Rancakalong-Sumedang (17.35 km) 91.13%

Section 3 Sumedang-Cimalaka (4.05 km) 100%

Section 4 Cimalaka-Legok (8.20 km) site clearing 39.71%

Section 5 Legok-Ujungjaya (14.9 km) clearing site 38%.

Section 6 Ujungjaya-Dawuan (6.06 km) section 6A 25%, and section 6B 2.3%.