Cisomang Bridge Reopened for All Vehicles

Cisomang Bridge Reopened for All Vehicles

Jakarta - The Ministry of Public Works and People's Housing (PUPR) said starting from Saturday, April 1, 2017 at 00.00 WIB, Cisomang Bridge located at KM 100 + 700 on the Purwakarta - Bandung - Cileunyi (Purbaleunyi) toll road segment of West Java By all classes of vehicles with a maximum axle load of 10 tons and a maximum vehicle load of 45 tons for 5 axles (Group V). The Ministry of PUPR observes the recommendations of the Bridge Security Commission and the Road Tunnel (KKJTJ) about the opening of traffic on Cisomang Bridge.

Previously, since December 23, 2016 ago, the PUPR Ministry has made traffic restrictions by allowing only Class I (Small - non bus) that can pass through the Cisomang bridge during the 3-month repair period. Within that period, the bridge handling is focused on 2 (two) things: stop the movement on the pillars and restore the strength of the bridge structure.

At present, based on continuous monitoring of movement and structure, all bridge pillars are in good condition. Being built to have the power to a standard in accordance with adequate safety factor, where the vehicle with overload is still not to bridge the Cisomang Bridge to ensure the safety of the community.

Cisomang Bridge handling is done with caution involving experts from various disciplines of science. In this case, the PUPR Ministry is accompanied by the Bridge Security Commission for Long and Road Tunnel (KKJTJ), LAPI ITB, and PT. Jasa Marga (Persero) as the toll road manager.

The repair of Cisomang Bridge has been done, among others: (1) stripping around A1 - P0 - P1, (2) installation of Steel Strutting connecting pillar P2 - P3, (3) Bored-pile installation on P2 and Soldierpile (4) installation of the Connection Beam from Pilecap Pillar P2 Grouting Epoxy on A1, P0, P1, P2, P5, A2, and (5) Carbon Reinforced Fiber Polymer (CFRP) as retrofitting P2 pillar , P3, and P4.

In the future, the Ministry of PWPH assigns PT. Jasa Marga (Persero) to implement 4 (four) things as follows:

Coordinate with the Indonesian Police Corps, Ministry of Transportation, and local government for the opening of traffic on 1 April 2017, with joint socialization activities from March 28, 2017 to March 31, 2017.

Continuous monitoring of the structure, soil / slopes, rivers and foundations of the Cisomang Bridge, as well as implementing permanent handling improvements to traffic may operate normally, by 30 September 2017 at the latest.

Preparing effective method for filtering / selecting non-Group I vehicles with overload that will cross the Cisomang Bridge.

Preparing SOPs if  the opening of traffic occurs things that are considered to endanger public safety as road users and bridges.

As a preventive step, the PUPR Ministry requested all Toll Road Enterprises (BUJT) to carry out continuous monitoring the condition of all long span bridges located on toll road sections under its management, so the risk of disruption to the bridge can be identified early and carried out with appropriate handling measures.

The integration policy is intended to reduce congestion on the toll road segments by eliminating transactions in some barrier gates, where the queues of vehicles will be distributed to each ramp so that overall travel time may be reduced. In addition, this policy is intended to encourage increased penetration of non-cash toll payment with the implementation of multi-bank e-payment system, as well as the initial initiative of Roadmap implementation of Electronic Toll Collection in Indonesia that is continuous, free flow in the next few years .

Integration of the toll road payment system is carried out on the following sections;

Jakarta-Cikampek Toll Road, Cikopo-Palimanan, Cipularang and Purbaleunyi or called Cluster 1 and Palimanan-Kanci Toll Road

Toll users who through Cluster 1 and 2 do card taking on ramp pay and off ramp pay payments.

Jakarta-Tangerang and Tangerang-Merak Toll Roads with this integration there will be changes as follows; A) Tomang-Cikupa: open system, flat rates. While on Cikupa-Merak segment: closed system, distance based. B) Vehicles from the direction of Jakarta to Bitung (Line A) transaction on Off Ramp Pay.

While on toll road users from the direction of Bitung to Jakarta (Line B) transactions conducted on On Ramp Pay. C) Barrier Karang Tengah gate is eliminated, the queue of vehicles on the main line will be distributed on each ramp. D) Construction of 5 new Toll Roads (GT) on the Jakarta-Tangerang Toll Road section.

Changes of Jagorawi Toll transaction system into open transactions of all segments of Cawang-Ciawi at a single rate with one transaction. Then the transaction of GT Cibubur Utama and Cimanggis Utama will be eliminated. Users from the direction of Jakarta to Ciawi will conduct transactions in off ramp (off ramp pay). Users of Ciawi to Jakarta route transactions on on ramp (on ramp pay). Users of SS Park Taman Mini-Ciawi walk on off ramp pay. Ciawi-Jakarta toll road users conduct transactions on on-ramp pay.

 

Integration of Jakarta Outer Ring Road (JORR) Toll Road or Jakarta Outer Ring Road with JORR W1 and JORR W2.

Share Berita Ini

Berita Terkait