regulation generally describes measurable 170 kilometers. On Andalas Island, the
stages in every land procurement step, Trans-Sumatra Toll Road has stretched for
from time limit to assignment of roles as far as 633 kilometers, divided into nine
between stakeholders. sections.
Unfortunately, this regulation has not been As of today, Law Number 11 Year 2020
fully implemented due to barriers including concerning Job Creation has been issued
discrepancy in regulations concerning while a Draft of Government Regulation
operational and supporting costs, as well as (RPP) on Land Procurement has been being
spatial compatibility. Other barriers include prepared. In general, this RPP is an attempt
tax incentive and litigation mechanism in to simplify Presidential Decree Number 71
relation to objection against compensation Year 2012 along with its derivatives.
value in district court. BADAN PENGATUR JALAN TOL
Simplification of these regulations
The Ministry of Agrarian Affairs and To be specific, according to data from the is a solution needed for accelerating
Spatial Planning/National Land Agency has Ministry of Public Works and Housing, the measurable land procurement process.
worked together with a number of related total amount of land needed for toll road It includes project implementation,
institutions to eliminate the bottleneck. construction is 37,340.99 hectares. More responsibilities of each institution, and
It includes, for example, coordination than half of the land needed for toll road is permit for extrication of land with specific
with the Ministry of Finance to discuss located in Sumatra. Until February 2021, characteristics such as forest, customary
tax incentive, operational and supporting as muny as 19,060.82 hectares of land, or land, village treasury land, and land for
costs, as well as acceleration of bailout 51 percent of the total land required, have sustainable food agriculture purpose.
payment by toll road business entities. been acquired.
It also includes coordination with the For example, the the Ministry of Agrarian
Supreme Court regarding procedures for This was what my team and I from the the Affairs and Spatial Planning is given
filing an objection. Ministry of Agrarian Affairs and Spatial authority to issue location allocation within
Planning did, specifically in toll road seven days if a governor fails to issue
So, Law Number 2 Year 2012 could finally project, either in ‘Trans-Java Toll Road’ or location allocation maximum 14 days after
be implemented after harmonizing all ‘Trans-Sumatra Toll Road’ projects. Good conclusion of the agreement.
regulations under this law in 2016. Since coordination with the Ministry of Public
then, the Ministry of Agrarian Affairs Works and Housing and the Indonesia Toll One of the aspects that has been adjusted
and Spatial Planning has received more Road Agency has made land procurement in Land Procurement RPP is the planning
challenging tasks given that, in the process in both toll corridors smooth. stage. In the planning document, all
same year, Presidential Decree Number aspects from spatial compatibility to land
3 Year 2016 concerning Accelerated Since 2019, Trans-Java Toll Road has status and compensation values need
Implementation of National Strategic connected Merak to Probolinggo, stretching updates. They are important to prevent
Project was issued. as far as 962 kilometers. It is now time barriers during the implementation stage.
to finish construction of Probolinggo-
This decree has been revised three times. Banyuwangi toll road, stretching as far as I recommend the Ministry of Public Works
Its most updated version is Presidential and Housing to collaborate with the
Decree Number 109 Year 2020. There are Ministry of Agrarian Affairs and Spatial
223 National Strategic Projects (NSP) and Planning as soon as they need land for
10 priority activities across Indonesia; 53 infrastructure projects. The Ministry of
of which are toll road construction projects. Agrarian Affairs and Spatial Planning will BADAN PENGATUR JALAN TOL
Nevertheless, challenges must be faced. help by mapping out objects for extrication,
Every problem has a solution. Solutions making procurement process faster.
can be found through coordination with
stakeholders and evaluation of the existing With careful preparation, intense
problems in each infrastructure project. coordination, and well-organized execution,
As a result, in 2020, land acquisition for land procurement process will be swift.
National Strategic Projects reached up to It will surely help achieve the target for
42,600 hectares. constructing 2,724 kilometers of toll road
by 2024.